Nghe An ranks second in the country in terms of site clearance progress for the North-South Expressway project.

Nguyen Hai December 31, 2019 10:55

(Baonghean.vn) - Deputy Minister of Transport Nguyen Nhat said so at a working session with the People's Committee of Nghe An province on speeding up the progress of the North-South expressway project through Nghe An on the morning of December 31, in Vinh city.

Comrade Le Hong Vinh - Member of the Provincial Party Committee, Vice Chairman of the People's Committee of Nghe An province chaired the working session with the delegation. Also attending were representatives of relevant departments, branches and districts.

Đồng chí Nguyễn Đức An - Phó Giám đốc Sở Giao thông Vận tải báo cáo kết quả triển khai giải phóng mặt bằng dự án cao tốc Bắc - Nam qua Nghệ An. Ảnh: Nguyễn Hải
Comrade Nguyen Duc An - Deputy Director of the Department of Transport reported on the implementation results of the North - South expressway project through Nghe An. Photo: Nguyen Hai

The North-South Expressway project, the section through Nghe An has 87.84 km passing through Hoang Mai town and the districts of Quynh Luu, Yen Thanh, Dien Chau, Nghi Loc and Hung Nguyen. Of which, 79.31 km passes through agricultural land, 8.53 km through residential land, and about 642 km of resettled households. The total estimated cost of site clearance is 2,762 billion VND, of which the Nghi Son - Dien Chau section is 1,261 billion VND and Dien Chau - Bai Vot is 1,501 billion VND; the project approval is 2,191 billion VND.

Sở đồ dự án cao tốc Bắc Nam đoạn phía đông qua địa bàn Nghệ An. Ảnh: Nguyễn Hải
Map of the North-South Expressway project, eastern section, through Nghe An. Photo: Document

Currently, the capital allocated for the project is 696.5 billion VND, of which the Nghi Son - Dien Chau section is 350 billion VND and the Dien Chau - Bai Vot section is 346.5 billion VND. The districts and towns have approved the measurement of 84.94km/87.84km, reaching 96.7%; approved the compensation plan of 709.76 billion VND, currently 541.4 billion VND has been paid, the length of land clearance is about 52.5/87.84km, reaching 59.77%.

Cao tốc Bắc Nam khi hoàn thành sẽ là tuyến giao thông huyết mạch của đất nước. Ảnh: Minh họa
The North-South Expressway, when completed, will be the country's vital traffic route. Photo: Illustration

At the meeting, Nghe An Department of Transport proposed that the Ministry of Transport approve the plan to relocate technical infrastructure works, the overall plan for site clearance; issue a handbook on compensation and resettlement support for localities; and soon supplement capital for localities to pay households, build resettlement, and relocate technical infrastructure works.

In addition, add some bridges and underpasses for people to suit; adjust the intersection of Dien Chau - Bai Vot with National Highway 7, build a fence to prevent re-encroachment after site clearance...

Đồng chí Nguyễn Nhật - Thứ trưởng Bộ Giao thông Vận tải thống nhất một số đề xuất của địa phương để đẩy nhanh tiến độ thi công dự án cao tốc Bắc Nam.Ảnh: Nguyễn Hải
Comrade Nguyen Nhat - Deputy Minister of Transport agreed with a number of local proposals to speed up the construction progress of the North-South Expressway project. Photo: Nguyen Hai

On behalf of the working delegation, comrade Nguyen Nhat - Deputy Minister of Transport acknowledged and appreciated the efforts and results of the Nghe An Party Committee and government in clearing the land for the North - South Expressway project. At the same time, he said that although only nearly 60% of the length has been cleared, Nghe An is the second province in the country in terms of land clearance progress (after Ninh Thuan).

The Deputy Minister also acknowledged the province's proposals on adding technical sewers and connecting roads to National Highway 7 arising from reality and assigned the Construction Management Department and Technical Committees to receive and complete plans to facilitate people's travel. The arrangement and adjustment of resettlement residential areas must be reasonable and in accordance with regulations.

In the coming time, if the procedures and documents are quick, the disbursement will be made and by mid-2020, investors can be selected. Regarding the plan to protect the liberated land and prevent re-encroachment, the Ministry has worked with the provinces to calculate and hand it over to the Boards to have the costs when there is an official technical design.

Comrade Nguyen Nhat - Deputy Minister of Transport

Đồng chí Lê Hồng Vinh - Phó Chủ tịch UBND tỉnh kết luận giao các địa phương và sở ngành nghiên cứu phương án kèm đề xuất bổ sung các hạng mục cụ thể. Ảnh: Nguyễn Hải
Comrade Le Hong Vinh - Vice Chairman of the Provincial People's Committee concluded, assigning localities and departments to study the plan with proposals to add specific items. Photo: Nguyen Hai

At the end of the working session, Mr. Le Hong Vinh - Vice Chairman of the Provincial People's Committee accepted the instructions of the working group, and assigned localities and departments to study and have plans with specific proposals for the province to consider. Proposals for resettlement support or housing arrangement must be based on legal regulations and considered in the general context of the province. /.